Project Background

Contractor repaired and constructed 5,300 feet of sidewalk on the south side of Baseline Road. Previously, the sidewalks were intermittent. The completion of the project made it convenient for pedestrians to walk to stores, schools and churches without being forced into the street to remain on solid surfaces. Contractor also included ramps for handicap access, curbing, and driveway cuts in the construction project.

Emission Tons CO Annual
0.00
Emission Tons CO Total
0.00
Emission Tons NOX Annual
0.00
Emission Tons PM Annual
0.00
Emission Tons PM Total
0.00
Emission Tons Rog Annual
0.00
Emission Tons Rog Total
0.00
Project Cost Description

125000.00

Project Implementation

The south side of Baseline Road in the City of Claremont now has continuous sidewalks. Areas north and south of Baseline benefit from a pedestrian standpoint and communities east of Claremont receive the benefit of cleaner air due to prevailing winds.

Project Results Description

Emission reductions were not calculated as the pedestrian traffic, which increased as a result of this project, was already emission free. The number of vehicles reduced due to this project was not measurable.

Project Status Description

Pictures of the sidewalks in various places, construction details, and explanations of the delays incurred.

Project Year
Summary Approved
No
Total Project Cost
$125,000.00
Co Funding Amount
$0.00
Project Category
Contractor Address
207 Harvard Avenue
Contractor Agency
City of Claremont
Contractor City
Claremont
Contractor Contact
Chistopher Viers
Contractor Country
United States of America
Contractor State
CA
Contractor Phone
Contractor ID
19
Contractor Zip
91711
Co Participants
Caltrans
Final Approval Date
Final Report Approved
No