Diesel Exhaust Aftertreatment Retrofit Program

Contract Number
PT06008
MSRC Award
$184,500.00
Project Background

The MSRC's 2005-06 Diesel Exhaust Aftertreatment Retrofit Program funds 50% of the cost of purchasing and installing a CARB-verified particulate trap or diesel oxidation catalyst, not to exceed a maximum of $4,500 per qualifying vehicle.

Emission Tons CO Annual
0.00
Emission Tons CO Total
0.00
Emission Tons NOX Annual
0.00
Emission Tons PM Annual
0.00
Emission Tons PM Total
0.00
Emission Tons Rog Annual
0.00
Emission Tons Rog Total
0.00
Project Cost Description

417000.00

Project Implementation

The City followed its procurement process to bid and award the contract.

Project Objectives

The City of Los Angeles will install diesel emission control systems on 41 ultra-low sulfur diesel powered solid resources collection vehicles. The 41 vehicles are part of a fleet of 116 ultra-low powered vehicles purchased by the City in 2005. All 116 vehicles were built with 2005/2006 Peterbilt 320 chasis, 10.3L Cummins ISM diesel engines, and 70-gallon fuel capacity.

Project State
California
Project Status Description

Porject is complete. Forty one (41) diesel exhaust aftertreatment devices were installed on the ultra-low sulfur diesel powered solid resource collection vehicles in late 2006. The 41 vehicles were immediately returned to service after installation of the devices.

Project Year
2006
Summary Approved
No
Total Project Cost
$417,000.00
Co Funding Amount
$232,500.00
Contractor Address
1149 S. Broadway Street, 8th Floor
Contractor Agency
City of Los Angeles, Bureau of Sanitation
Contractor City
Los Angeles
Contractor Contact
Kim Tran
Contractor Country
United States of America
Contractor State
CA
Contractor Phone
Contractor ID
0
Contractor Zip
90015
Final Approval Date
Final Report Approved
No